Old Town Hall Construction Update

Navigation Links

Construction Update | Photos 


Please Note: Updates to be posted as they are provided by the Meadows Construction Company, the contractor and the Clerk of the Works, the renovation project manager. Please keep in mind these updates are subject to change at any time due to weather or various other extenuating circumstances.

SCHEDULE
June 29th-August 2nd
a) Chimney brick work – complete Sub Contractor-Chapman Waterproofing
b) HVAC Rough – complete Sub Contractor-Merrimack Valley
c) Plumbing and Gas Piping – complete Sub Contractor-Cashman Plumbing and Heating
d) Window Sash Installation – ongoing
e) Electrical-rough – ongoing Sub Contractor-MercierElectric
f) Demo Front Porch Deck
g) Elevator Install- complete Sub Contractor-Buckley Lift Company

August 5th-9th
a) Window Sash Installation – complete
b) Start Perimeter Drain Installation
c) Dig and Pour Head Wallfor Handicap Ramp and Concrete Piers
Sub Contractor-Sampson Concrete Company
d) Electrical Rough – complete Sub Contractor-Mercier Electric
e) Gas Pipe, Plumbing, Electric and Building Inspections – Town of Tyngsboro
f) Raise Existing Granite Steps Sub Contactor-Chapman Waterproofing
g) Elevator Block work-complete Sub Contractor-Chapman Waterproofing

August 12th-16th
a) Clean OutBuilding Completely
b) Start Spray Foam Insulation Sub Contractor-Steve DesJardins Construction
c) Frame New Front Entrance Deck
d) Complete Perimeter Drain
e) Start Exterior Painting Sub Contractor-Dandis Contracting
August 19th-23rd
a) Spray Foam Insulation – complete Sub Contractor-Steve DesJardins Construction
b) Fire Stop and Blocking
c)Inspections ofInsulation, Fire Stops,Blocking and Framing -Town of Tyngsboro
d) Exterior Painting – ongoing Sub Contractor-Dandis PaintingPage 2 of 3

August 26th-30th
a) Start Metal CeilingWork Ground Floor and Sheetrock Sub Contractor-CRL DrywallInc.
b) Handicap Ramp and Concrete Pad South Entrance – complete Sub Contractor-Sampson Concrete
c)Install Flag Pole Concrete Piers
d) Repair existing Granite Wall
e) Exterior painting – ongoing Sub Contractor-Dandis Contracting
Sept. 2nd – 6th
a) Exterior Painting – ongoing Sub Contractor-Dandis Contracting
b) Sheetrock – ongoing Sub Contractor-CLR DrywallInc.
c) Walk Way Pavers – complete
d) Concrete Side Walk – complete Sub Contractor-Sampson Concrete

Sept.9th -13th
a) Sheetrock – complete Sub Contractor-CRL DrywallInc.
b) Exterior Painting – complete Sub Contractor-Dandis Contracting
c)Interior Ceiling and Walls(Primer and Painting) – start Sub Contractor Dandis Contracting
d) Landscaping – complete

Sept. 16th-20th
a)Interior Wall and Ceiling Painting – complete Sub Contractor-Dandis Contracting
b)Interior TrimWork Delivery

Sept. 23rd-27th
a) Start Interior Trim Work
b) Cabinet Delivery
October 1st -4th
a)Interior Trim Work– ongoing
b)Installation of Cabinets – complete
c) Electrical Lighting – ongoing Sub Contractor Mercier Electric
d) Suspended Ceiling Work – complete
October 7th-11th
a)Interior Trim Work – ongoing
b)Interior HVAC Grills – ongoing Sub Contractor-Merrimack Valley
c)Interior Electrical Lighting – ongoing Sub Contractor Mercier Electric
d)Interior Staining and Painting – ongoing Sub Contractor-Dandis ContractingPage 3 of 3
October 14th-18th
a)Interior Trim Work – complete
b)Interior Stain & Painting – ongoing
c) Delivery of Hardwood Floors
d) Granite Counter TopsInstalled
October 21st-25th
a)Interior Hardwood Floor – ongoing
b)Interior Staining and Painting – complete Sub Contractor-Dandis Contracting
c)Interior Trim hardware – complete
d) StartTile Work starting with Bathrooms
October 28th-November 1st
a) Tile Work– ongoing
b) Hardwood Flooring – complete
c) Finish HotTop Driveway – complete
November 4th-8th
a) Plumbing Finish – complete Sub Contractor-Cashman Plumbing
b) HVAC Finish – complete Sub Contractor-Merrimack Valley
c) Electrical Finish – ongoing Sub Contractor-Mercier Electric
d) Elevator and Chair Lift Finish- complete Sub Contractor-Buckley Lifts
e) Tile Work Ground Floor – ongoing
November 11th
-15th
a) Electrical Finish – ongoing Sub Contractor-Mercier Electric
b) Tile Work – complete
c)Install GrabBars and Bath Accessories
November 18th-22nd
a) Electrical Finish – ongoing
b) Touch up Painting
November 25th -29th
a) Electrical Finish Fire Alarms – complete Sub Contractor-Mercier Electric
b) Finish Coat On All Hardwood Floors
December 2nd-6th
a) Fine Tune and Touch Up
b) Final Inspections
c) CLOSE OUT